The 2026 midterms and data center development
Ohio and Texas elected new governors who campaigned for tougher data center conditions. Local voters also changed the approval path for specific developments.
Published November 9, 2026 · Election and policy review through November 4, 2026
Ohio
Amy Acton’s conditional-moratorium proposal puts utility costs, labor and community benefits at the center of the incoming administration’s agenda.
Texas
Gina Hinojosa called for a pause pending legislation on public participation, water, power costs and subsidies.
Two changes in governors, two policy agendas
Democrats Amy Acton and Gina Hinojosa won the Ohio and Texas governor’s races, according to AP calls carried by OPB and KPRC. Both campaigned for tighter conditions on data center development. Their proposals give investors and developers a concrete policy agenda to monitor as the administrations take office in 2027.
The election calls are not new permitting orders. Existing permits, pending applications and later phases must be assessed against the rules that apply to each project.
Ohio: conditions on costs and community benefits
Acton’s July 27 platform supports a conditional moratorium unless projects cover their utility costs, use union construction labor, operate transparently, meet environmental standards and support local communities. It also emphasizes investment in former industrial areas.
This sits alongside an existing, narrower action: Governor Mike DeWine’s pause on new data center tax-exemption requests. That incentive pause should not be described as a statewide prohibition on construction.
For a proposed Ohio campus, the records to watch are the new administration’s orders, incentive decisions, utility cost-allocation terms and any changes to environmental review. Local zoning and siting decisions remain separate parts of the project history.
Texas: water, power and a legislative pause
Hinojosa’s July 23 platform called for a moratorium until the legislature addresses data centers. Her priorities include public participation, disclosure, union labor, protection against utility cost shifts, an end to subsidies and safeguards for community water supplies.
The starting point is not an unrestricted state regime. Governor Greg Abbott had already issued a September TCEQ permitting directive. The transition analysis therefore needs to distinguish inherited restrictions from Hinojosa’s proposed changes.
Developers should track the scope of any new order, which applications and phases it covers, and how legislative changes affect water contracts, incentives and utility service. A campaign proposal alone does not determine a project’s legal status.
Local votes changed specific approval paths
Ashville, Ohio
Scioto Post reported that voters rejected the EdgeConneX development term summary in the November 3 referendum. The action concerns the council’s negotiated framework. It should be recorded separately from the status of individual zoning, environmental or construction approvals. The reviewed result was election-night reporting, not a certification record.
Janesville, Wisconsin
Channel 3000 reported that voters approved a requirement for future voter approval of major development at the former GM/JATCO site. That creates another local decision point. It is not a blanket data center ban. The reviewed result was reported following the election and was not presented as certified.
What we will track next
The material changes will appear in executive orders, legislation, agency instructions, utility proceedings and local decisions. Our research links those actions to the campuses and jurisdictions they affect, preserving the distinction between a proposed rule, an adopted restriction and a project-specific outcome.