Utah data center policy

State policy, local approvals and the questions that shape development in Utah.

Research baseline: September 27, 2026. Published November 9, 2026.

State policy context

A law signed on 25 March 2025 moved loads of 100 MW or more onto a separate track: contracts reviewed by the PSC, ring-fenced accounting and the option to buy or build their own generation. The rule implementing it took effect on 1 January 2026 and is already being amended, with a flexible large-load tariff promised by year-end. The 2026 session added water reporting and limits on local tax incentives, and Governor Cox's executive order of 29 May 2026 set a 'higher bar' policy. The data center sales tax exemption stands.

What to check for a proposed site

The state-level position is the starting point. A project in Utah also needs a site-specific review of the city or county’s land-use rules, any adopted local restrictions, and the conditions attached to its approvals. A tax incentive or announced investment does not establish permission to build.

Track the serving utility’s large-load process alongside air permits for generators, water supply and wastewater arrangements, construction stormwater, and any applicable federal waters authorization. The required sequence depends on the parcel, equipment and design.

This public page summarizes the dated research baseline above. It is not a live inventory of every local measure or a determination that a particular parcel is eligible.