Florida data center policy

State policy, local approvals and the questions that shape development in Florida.

Research baseline: September 27, 2026. Published November 9, 2026.

State policy context

A new law signed on 7 May 2026 and in effect from 1 July 2026 defines a large load customer as one with a monthly peak of 50 MW measured over a 15-minute interval. Each utility must file a tariff by 1 October 2026 under which every such customer pays its full cost of service. The law also stops utilities serving foreign-entity large loads, adds new tests for water-use permits, requires large data centers to use reclaimed water, and confirms that local governments keep their zoning authority. Separately, the state sales tax exemption requires $150 million of investment and 100 MW of critical IT load. That threshold was raised from 15 MW by a 2025 law that took effect on 1 August 2025, and the new law left it unchanged.

What to check for a proposed site

The state-level position is the starting point. A project in Florida also needs a site-specific review of the city or county’s land-use rules, any adopted local restrictions, and the conditions attached to its approvals. A tax incentive or announced investment does not establish permission to build.

Track the serving utility’s large-load process alongside air permits for generators, water supply and wastewater arrangements, construction stormwater, and any applicable federal waters authorization. The required sequence depends on the parcel, equipment and design.

This public page summarizes the dated research baseline above. It is not a live inventory of every local measure or a determination that a particular parcel is eligible.