Delaware data center policy

State policy, local approvals and the questions that shape development in Delaware.

Research baseline: September 27, 2026. Published November 9, 2026.

State policy context

On 26 August 2026 Governor Meyer signed four bills. The first requires facilities above 75 MW to produce or buy 100% of their annual energy from clean sources before they can connect. That power can come from neighbouring PJM zones. Projects lock it in through a 15-year PSC contract backed by a bond, or on an approved 10-year ramp. The second creates a separate large-load rate class that pays full infrastructure costs and is curtailed first in an emergency. The third bars job-creation tax credits for these facilities. The fourth bans public bodies from signing NDAs on projects of 100 MW or more.

What to check for a proposed site

The state-level position is the starting point. A project in Delaware also needs a site-specific review of the city or county’s land-use rules, any adopted local restrictions, and the conditions attached to its approvals. A tax incentive or announced investment does not establish permission to build.

Track the serving utility’s large-load process alongside air permits for generators, water supply and wastewater arrangements, construction stormwater, and any applicable federal waters authorization. The required sequence depends on the parcel, equipment and design.

This public page summarizes the dated research baseline above. It is not a live inventory of every local measure or a determination that a particular parcel is eligible.