Arkansas data center policy
State policy, local approvals and the questions that shape development in Arkansas.
Research baseline: September 27, 2026. Published November 9, 2026.
State policy context
Arkansas is actively recruiting. A law signed on 10 April 2025 widened the 2023 sales and use tax exemption by cutting the minimum investment from $500 million to $100 million, and added a large data center category for projects spending $2 billion over ten years. It was signed without an emergency clause, so it applied from 1 October 2025. The Generating Arkansas Jobs Act, in effect since 20 March 2025, lets utilities recover infrastructure costs before construction is complete, so new plants can be billed early. Six 2026 resolutions aimed at data centers died when the legislature adjourned on 29 April 2026.
What to check for a proposed site
The state-level position is the starting point. A project in Arkansas also needs a site-specific review of the city or county’s land-use rules, any adopted local restrictions, and the conditions attached to its approvals. A tax incentive or announced investment does not establish permission to build.
Track the serving utility’s large-load process alongside air permits for generators, water supply and wastewater arrangements, construction stormwater, and any applicable federal waters authorization. The required sequence depends on the parcel, equipment and design.
This public page summarizes the dated research baseline above. It is not a live inventory of every local measure or a determination that a particular parcel is eligible.