Arizona data center policy

State policy, local approvals and the questions that shape development in Arizona.

Research baseline: September 27, 2026. Published November 9, 2026.

State policy context

The 2026 budget, signed on 13 June 2026, stops the Commerce Authority from accepting new data center tax-exemption applications from 1 July 2026 through 30 June 2029. Existing certifications are untouched. A second law, signed on 4 June 2026, makes utilities report twice a year on large-load connections and lets the Arizona Corporation Commission set contract terms so other customers do not end up paying for data center costs. The ACC's general review of large loads has held one workshop so far. APS's proposed large-load changes wait on a rate case decision expected in late 2026. Governor Hobbs rejected a statewide moratorium on 3 September 2026.

What to check for a proposed site

The state-level position is the starting point. A project in Arizona also needs a site-specific review of the city or county’s land-use rules, any adopted local restrictions, and the conditions attached to its approvals. A tax incentive or announced investment does not establish permission to build.

Track the serving utility’s large-load process alongside air permits for generators, water supply and wastewater arrangements, construction stormwater, and any applicable federal waters authorization. The required sequence depends on the parcel, equipment and design.

This public page summarizes the dated research baseline above. It is not a live inventory of every local measure or a determination that a particular parcel is eligible.

Sources and further reading