Data centers in space:
U.S. approvals

A guide to U.S. approvals for orbital data centers, from satellite authorization to launch and operations, using SpaceX’s Starmind application.

On November 25, 2026, SpaceX received FCC authorization for its Starmind orbital data-center system, covering up to one million satellites. The FCC imposed conditions and deferred a request concerning satellite disposal.

The decision brings the approval process for orbital computing into focus. This guide explains the agencies involved, the applications they review and the requirements that continue after an authorization.

Regulators and responsibilities

An orbital data center combines a spacecraft, a communications system and a launch mission. Each brings its own review. Applications can progress in parallel; the mission must meet the applicable conditions before the relevant operation begins.

Federal Communications Commission

The FCC authorizes the satellite system’s radio operations and imposes conditions on spectrum use, interference, orbital debris and deployment. The scope depends on the application, including requested rule waivers.

Read the grant: approved frequencies, orbital configuration, conditions and any deferred requests.

Example: Starmind authorization

Federal Aviation Administration

The FAA licenses commercial launch and reentry operations. A vehicle operator’s authorization and the relevant site permissions must cover the mission. Payload review normally sits within this process and can also be requested in advance.

Before flight: confirm the licensed mission, payload review and applicable safety requirements.

FAA licensing overview

FCC and relevant local authorities

Radio gateway earth stations need the applicable FCC authority. Physical ground facilities also need a location-specific review of land use, construction and environmental requirements. Existing facilities may already hold some permissions.

Before use: check that each gateway’s authorization covers the proposed communications.

Starmind grant, condition 1

Department of Commerce

A private Earth remote-sensing mission can trigger Commerce licensing through its Commercial Remote Sensing Regulatory Affairs office. Requirements follow the mission’s actual capabilities. Hosting computing hardware alone does not establish an Earth remote-sensing activity.

At design stage: identify additional payload functions and consult the responsible agencies.

Commerce remote-sensing licensing

Approval process

1

Define the mission and the applicants

Set out the orbit, fleet size, communications, ground stations, launch arrangements and disposal plan. Identify which permissions belong to the satellite operator, launch provider and ground-station operator.

2

Submit applications and answer the record

The FCC process can include public notice, comments, petitions to deny and applicant responses. Technical coordination and additional information may be needed. For Starmind, the application was filed January 30 and accepted for filing February 4, 2026, before the November decision.

3

Close conditions before the relevant operation

Check the exact scope of every grant. FAA payload review examines required authorizations while respecting FCC and Commerce jurisdiction. FAA launch and reentry licensing also requires the applicable environmental review and finding.

FAA payload reviewFAA environmental review
4

Operate within the license and report changes

Track deployment deadlines, interference obligations, debris mitigation and reporting. Changes to the authorized system may require a modification application. International spectrum filings and coordination also matter: Starmind must operate consistently with its ITU filings and submit changes to the FCC before modifying its configuration.

SpaceX’s FCC approval, November 2026

The FCC granted part of SpaceX’s Starmind application, deferred part and imposed conditions. The authorization covers a constellation of up to one million orbital data-center satellites.

Radio backup for an optical network

The grant permits backup and emergency telemetry, tracking and command in specified Ka-band frequencies. Starmind primarily uses optical links. Its authorized radio operations must protect other users from interference.

Disposal and ground links

The FCC deferred the alternative-disposal waiver. The order requires a modification application with a final debris plan before deployment above 600 km. Required gateway earth-station authorizations must also be obtained before those communications begin.

The order also requires continuing coordination and semiannual operational reports. FCC authorization establishes the licensed scope and obligations. Launch authorization, deployment, commissioning and usable computing capacity each require further execution.

Deployment deadlines in the grant

2033November 25

First satellite deployed and operating

2035November 25

10% of the authorized fleet

2038November 25

50% of the authorized fleet

2040November 25

Remaining authorized satellites

FCC order DA 26-1273: grant conditions 1, 4-6 and 10; paragraphs 11 and 20

Upcoming filings and milestones

For an orbital data-center project, the useful question is how much of the proposed system the current permissions allow to operate, and which conditions still constrain deployment.

Scope changes

Modification applications, disposal plans and any new waiver decisions.

Mission readiness

Applicable launch authorization, gateway permissions and completed coordination.

Evidence of delivery

Deployed satellites, operational certifications, reporting and demonstrated computing service.

This guide summarizes the U.S. process and the cited Starmind order as of November 25, 2026. Other missions and jurisdictions can require additional permissions.

Source documents

FCC - SpaceX Starmind order and authorization, November 25, 2026FAA - Licenses, permits and approvalsFAA - Payload reviewsFAA - Environmental review for commercial space operationsOffice of Space Commerce - Commercial remote-sensing licensing

Follow the approval record.

RegLayer tracks the decisions, conditions and infrastructure milestones that shape project delivery.

Talk to RegLayer