Data centers in space:
U.S. approvals
A guide to U.S. approvals for orbital data centers, from satellite authorization to launch and operations, using SpaceX’s Starmind application.
On November 25, 2026, SpaceX received FCC authorization for its Starmind orbital data-center system, covering up to one million satellites. The FCC imposed conditions and deferred a request concerning satellite disposal.
The decision brings the approval process for orbital computing into focus. This guide explains the agencies involved, the applications they review and the requirements that continue after an authorization.
SpaceX’s FCC approval, November 2026
The FCC granted part of SpaceX’s Starmind application, deferred part and imposed conditions. The authorization covers a constellation of up to one million orbital data-center satellites.
Radio backup for an optical network
The grant permits backup and emergency telemetry, tracking and command in specified Ka-band frequencies. Starmind primarily uses optical links. Its authorized radio operations must protect other users from interference.
Disposal and ground links
The FCC deferred the alternative-disposal waiver. The order requires a modification application with a final debris plan before deployment above 600 km. Required gateway earth-station authorizations must also be obtained before those communications begin.
The order also requires continuing coordination and semiannual operational reports. FCC authorization establishes the licensed scope and obligations. Launch authorization, deployment, commissioning and usable computing capacity each require further execution.
Deployment deadlines in the grant
2033November 25First satellite deployed and operating
2035November 2510% of the authorized fleet
2038November 2550% of the authorized fleet
2040November 25Remaining authorized satellites
FCC order DA 26-1273: grant conditions 1, 4-6 and 10; paragraphs 11 and 20
Upcoming filings and milestones
For an orbital data-center project, the useful question is how much of the proposed system the current permissions allow to operate, and which conditions still constrain deployment.
Scope changes
Modification applications, disposal plans and any new waiver decisions.
Mission readiness
Applicable launch authorization, gateway permissions and completed coordination.
Evidence of delivery
Deployed satellites, operational certifications, reporting and demonstrated computing service.
This guide summarizes the U.S. process and the cited Starmind order as of November 25, 2026. Other missions and jurisdictions can require additional permissions.